Agile Project Management vs. Critical Path Method

The Critical Path Method (CPM) of project management is very commonly used in the management of construction projects.

D. Brown Management Profile Picture
Share

CPM works very well when the components of the design and the project are mostly known to all responsible parties. CPM focuses on either a single value-delivery event such as the completion of a building or in major phases such as turning over a floor at a time.  

Management Tools: Agile Project Management vs Critical Path Method (CPM).

CPM does not work as well in situations where there are significant “Known-Unknowns” about the plan CPM really breaks down when there are “Unknown-Unknowns”:

  • The final destination isn’t crystal clear; even to the leader
  • The path to get there has unknowns
  • The tools and tactics required to get there aren’t known to the team

In these situations more agile management methods are required either in conjunction with or to replace CPM:

There are similarities between all methods.  Develop the systems that work best for your company at this point in time.




Production Tracking - Total Daily Production
Look at productivity as a daily “Jar” where your objective is to pack as much “Earned Value” into it as possible. Look at your costs in three major categories and focus on tracking what matters the most.
Organizational Structures and Leadership Development
As contractors look at their organizational structures with an eye toward both sustainable growth and succession, they must balance the efficiency a functional area structure provides with the leadership development of a business unit structure.
Want Does Not Create Capability
Having a vision, want or even a need means nothing. It is only through planning, hard work and time that you will achieve your goals.