Change Orders and Average Cost Impact to the Project (Industry Survey)

Changes are a part of the construction process with many underlying causes.

D. Brown Management Profile Picture
Share

While we have all heard the average of 10% changes on construction projects, it is interesting to look at an industry study for validation.  

Change Management: Project Changes, state of the industry survey.

This study by HBRC categorized the range of contract changes and the percent of projects within that range. The average is 10% and none of the projects had 0% changes.  

Engaging key contractors to work on the project earlier will lower the amount of changes related to design conflicts while protecting the aesthetics of the design.  

Another interesting part of the study was that 43% of respondents DID NOT have a consistent process for managing changes.  

A rigorous change management process starts at the earliest stages of design development with rigorous weekly reviews.  

During construction, the definition of a change should be broadened beyond what may become a cost issue for the project owner and also managed through a rigorous weekly process such the Last Planner System.  


Change Orders and Average Cost Impact to the Project (Industry Survey)
Change orders are a fact of life in construction. Improve profitability, cash flow and customer satisfaction by effectively managing changes. Build a foundation for success with 12 steps to improve pricing and 11 negotiating strategies for the whole project team....

Related Training
Change Orders and Average Cost Impact to the Project (Industry Survey)
Change orders are a fact of life in construction. Improve profitability, cash flow and customer satisfaction by effectively managing changes. Build a foundation for success with 12 steps to improve pricing and 11 negotiating strategies for the whole project team....

Clear Installation Information
For a contractor to maximize their labor productivity, they need to start with clear information provided to the crews doing the actual installation. Good information is the first of the six pillars of productivity and means several things:
Building an Effective Preconstruction Team
Your precon team is your company from the perspective of the project owner. Put your best foot forward by selecting the right people in the right roles at the right stage of the project.
Early Identification is a Process - Effectively Using Checklists
Few things will improve customer satisfaction, profitability, cash flow, risk, and team stress more than early identification of change orders. This is a process and a trainable skill. Checklists are some of the most valuable tools in that process.