Impacted Productivity - Disrupted Workflow (No Schedule "Flow")

One of the biggest impacts to productivity in construction is when tasks can not be completed as planned.

D. Brown Management Profile Picture
Share
Field Productivity: Impacts - Disrupted Workflow.

 

  • The project schedule for other trades and tasks must be adjusted often, causing overall project delays, increased “Bad Stress” on the project team, or both.  
  • The actual task itself costs more than budgeted by contractor. At a minimum, the interruption will cost additional mobilization to and from the work area. Remember that about 19% of the labor hours in a typical construction day are spent figuring out what to do, gathering materials, and site movement. When a task is interrupted, you often have to repeat some or all of these non-installation tasks.  

When this happens frequently, it starts to impact every aspect of the contractor’s scoreboard in a negative way starting with customer satisfaction.

Weekly feedback and learning systems are a core element of the Last Planner System because their research showed that tasks not being completed as planned were the single biggest source of poor project performance.  

 

Focusing on planning Effective Tasks, the 6 Pillars of Productivity, and ABC Daily Planning will keep your project on-track.  

 


Impacted Productivity - Disrupted Workflow (No Schedule "Flow")
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Impacted Productivity - Disrupted Workflow (No Schedule "Flow")
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

A Broader Definition of a Change on a Construction Project
The first step for contractors improving their management of changes on a project is simply earlier identification. This starts with a better definition of what a change really is, and then setting standards within your company around that definition.
Changes and Cash Flow Improvement
Construction is a cash-intensive business and change orders are often one of the root causes of poor cash flow. A 30-day improvement to change management workflow can generate over $400K in additional cash flow for a $50M contractor.
Four Critical Elements of an Effective Task
Maximizing labor productivity starts with defining exactly what needs to be delivered and then breaking it down into tasks that can be effectively managed.