Impacted Productivity - Disrupted Workflow (No Schedule "Flow")

One of the biggest impacts to productivity in construction is when tasks can not be completed as planned.

D. Brown Management Profile Picture
Share
Field Productivity: Impacts - Disrupted Workflow.

 

  • The project schedule for other trades and tasks must be adjusted often, causing overall project delays, increased “Bad Stress” on the project team, or both.  
  • The actual task itself costs more than budgeted by contractor. At a minimum, the interruption will cost additional mobilization to and from the work area. Remember that about 19% of the labor hours in a typical construction day are spent figuring out what to do, gathering materials, and site movement. When a task is interrupted, you often have to repeat some or all of these non-installation tasks.  

When this happens frequently, it starts to impact every aspect of the contractor’s scoreboard in a negative way starting with customer satisfaction.

Weekly feedback and learning systems are a core element of the Last Planner System because their research showed that tasks not being completed as planned were the single biggest source of poor project performance.  

 

Focusing on planning Effective Tasks, the 6 Pillars of Productivity, and ABC Daily Planning will keep your project on-track.  

 


Impacted Productivity - Disrupted Workflow (No Schedule "Flow")
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Impacted Productivity - Disrupted Workflow (No Schedule "Flow")
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Underlying Causes of Changes on Projects
Start improving your change management skills by creating some categories of the underlying causes of changes your company experiences.
Lean Principle - Pulling vs. Pushing and the Four Most Powerful Words for Improving Productivity
“What do you need?” are the four most powerful words for improving productivity, developing a team, and building engagement. "Pull-Planning" can be used way beyond building a project. The principle is the foundation for many aspects of life and business.
Impacted Productivity - Five Elements of Making a Good Case
Contractors are continually faced with costly impacts to their labor productivity and schedule with many beyond their direct control. The best Project Managers know how to identify, communicate, and mitigate these impacts.