Planning - Integrating the 4 Key Responsibilities

There are four major responsibilities the foreman has that often seem to be competing with each other.

D. Brown Management Profile Picture
Share

Effective planning combined with regular feedback (at least weekly) combined with a structured look at how to improve each week is the key to integrating these four key responsibilities of a Foreman

Field Productivity: Planning, Integrating the four key responsibilites. Safety, Production, Customer Satisfaction, and Quality.

Greg Howell and Glen Ballard founded the Lean Construction Institute (LCI) based on analysis of construction projects showing that on average only 54% of the tasks planned for a week by the Foreman actually got completed. 

They developed The Last Planner System (LPS) that focuses on helping the Foreman plan then execute more effectively.  

The system includes a structured weekly learning element for the project team where they look back at what they accomplished measuring their Percent Plan Complete (PPC) and doing some rapid Root Cause Analysis to improve the process for the following week.  

PPC is a simple measurement - the quantity of tasks that were completed during the week compared to those that were planned.  This is described well in this whitepaper from LCI.

These tools are best used for a whole project team but can be effectively used by a single contractor on a project.  


Planning - Integrating the 4 Key Responsibilities
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Planning - Integrating the 4 Key Responsibilities
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Changes - Problem or Fact?
If you perceive that changes are a problem in construction, then you are likely framing them as a point of blaming others. This framing will impact your ability to effectively manage changes.
Resource - The Five Minute Foreman
The Five-Minute Foreman by Mark Breslin is our most recommended book for Foremen in any sized contractor. The writing style, digestible chunks, and companion workbook are a great combination. We have never heard any Foreman not absolutely love this book.
Changes and Cash Flow Improvement
Construction is a cash-intensive business and change orders are often one of the root causes of poor cash flow. A 30-day improvement to change management workflow can generate over $400K in additional cash flow for a $50M contractor.