Production Tracking - Changing the Language

Your productivity will start to really improve as it becomes a culture and not just a tracking system.

D. Brown Management Profile Picture
Share
Field Productivity: Troubleshooting Problems when Production Tracking.

You will first notice this as a change in language in the field and across the whole project team:

--- EXAMPLE ---

FROM:  The job superintendent is disorganized and skipping us all over the project.

TO:  We are being moved all over the job site due to plan coordination errors.  Our framing productivity has been 78% of target for the last 3 days.  


How do you talk?

How does your team talk?

What can you do to improve?

What would that be worth?


Improving Labor Productivity Workshop


Production Tracking - Changing the Language
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Production Tracking - Changing the Language
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

The Risks of Vision and Strong Leadership
The strongest leaders at all levels in construction have a clear vision of where they are headed and are relentlessly focused on achieving their goals. They align their teams tightly around the vision, goals, and strategy. This may introduce risks.
Build Your Most Valuable Asset
There are five main value levers that contractors can pull to truly increase the value of the business as measured in long-term return on capital and valuation during a succession.
Planning is Useless
Planning how to build a project and planning how to build a contracting business are VERY different and must be approached with a different mindset. When planning ‘how’ to build a project the ‘what’ is mostly known.