Production Tracking - Changing the Language

Your productivity will start to really improve as it becomes a culture and not just a tracking system.

D. Brown Management Profile Picture
Share
Field Productivity: Troubleshooting Problems when Production Tracking.

You will first notice this as a change in language in the field and across the whole project team:

--- EXAMPLE ---

FROM:  The job superintendent is disorganized and skipping us all over the project.

TO:  We are being moved all over the job site due to plan coordination errors.  Our framing productivity has been 78% of target for the last 3 days.  


How do you talk?

How does your team talk?

What can you do to improve?

What would that be worth?


Improving Labor Productivity Workshop


Production Tracking - Changing the Language
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Production Tracking - Changing the Language
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Creating an Operating Rhythm
What are the critical meetings, communications and feedback systems that keep your contracting business running like clockwork?
CM-at-Risk: The Preferred Delivery Method of the Top 400 Largest Contractors
Construction Manager-at-Risk (CMAR) is the preferred project delivery method for the ENR Top 400 contractors and the project owners they serve.
Problem-Resolution Cost Pyramid - Earlier is Always Better
An easy way to visualize the cost of problem resolution at different stages of construction is with this pyramid. The cost of the problem is the cost of the problem (1X). Finding it ahead of time minimizes the costs and maximizes customer satisfaction.