Production Tracking - Lessons Learned

Production and production tracking will never be perfect.

D. Brown Management Profile Picture
Share

Production tracking is just one part of an overall system for managing projects. The magic is developing a culture of continuous improvement across the whole team.  Some lessons learned when it comes to effective production tracking:

Field Productivity: Production Tracking. Lessons Learned. Start Small, Build Trust, Crews not Individuals, Days not Tasks, What-If Analysis, Experimentation, Selective Overtime, Small Rewards, and Refining Process.
  1. Start small testing and refining the process on one project or just a few tasks.
  2. Build trust across the field leadership and crews.  This is a tool for them to help them get better including learning to troubleshoot production.  It IS NOT a “monitoring” mechanism.  
  3. Focus on crew productivity rather than individuals.  Teach teams how to organize people for maximum impact.
  4. Focus on maximizing daily and weekly productivity; not just single tasks. Daily Production
  5. Develop tools, training and a habit of the team doing “What If” analysis to find the best way to execute before starting.  It is cheaper to figure this out on paper or virtually than it is physically.
  6. Make sure your culture supports consistent use of the best installation standards you have learned across all crews.  And provide room for smart EXPERIMENTATION to find the next best standard. PDCA
  7. Use selective overtime to meet daily production goals where applicable.  
  8. Use small rewards that are very short-interval (daily & weekly) and supervisor driven.  Combined with an overall performance compensation system this will build morale and sustainable results. 
  9. Technology is amazing but make sure your field supervisors can create an effective tracking tool including motivating the crew using a piece of sheetrock, spray paint and construction crayon.  People; then effective processes and then tools. 

Improving Labor Productivity Workshop


Production Tracking - Lessons Learned
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Production Tracking - Lessons Learned
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Learn from the Wisdom in the Lessons of History
“Fortune favors the prepared mind.” - Louis Pasteur ---------- How much time do you and your team spend exploring the broader context of our world?
Competition - What Do You Really Know?
Contractors typically pay too much or too little attention to their competition. The best contractors strike the right balance spending most of their time focused on customers while being deliberate in knowing their competition.
Stages of Development - The Seven Habits of Highly Successful People
Building even a simple construction project requires coordinating 100+ people. While we may like to think of ourselves as 'independent,' it is not the highest stage of development.