Time-on-Tools and Minimum Required Installation

Labor productivity IS NOT the biggest problem with field productivity. Under similar conditions the variation in how fast two crafts people actually “turn wrenches” is about 2X but there are far bigger problems to tackle. Focus on these three areas.

D. Brown Management Profile Picture
Share

 

Field Productivity: Labor Productivity IS NOT The Biggest Problem With Project Productivity

 

  1. Maximize Time-on-Tools (ToT): Ensure that crafts people spend most of their day working with their tools actually installing things.  Different studies place the industry average between 50-65%.  Leverage the 6 Pillars of Productivity and ABC Daily Planning.  
  2. Minimum Required Installation (MRI): Don’t take critical shortcuts but don’t over-build the project.  In the field we would call it “Gold Plating.” Effective installation details, craft training and good field supervision practices will ensure that you get the right level of quality. 
  3. Minimize Rework: The only greater waste than installing more than what is required is doing it twice.

General Contractors and Project Owners can do a lot to set the conditions for success with their labor-intensive subcontractors. 


4 Elements of an Effective Task

Site Logistics Management


Time-on-Tools and Minimum Required Installation
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Time-on-Tools and Minimum Required Installation
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Resource - The Five Minute Foreman
The Five-Minute Foreman by Mark Breslin is our most recommended book for Foremen in any sized contractor. The writing style, digestible chunks, and companion workbook are a great combination. We have never heard any Foreman not absolutely love this book.
The Six Pillars of Task Productivity in the Field
Contractors can guarantee labor productivity on their projects by leading their project teams to focus relentlessly on ensuring that these 6 Pillars of Productivity are supporting each task on the job site.
Underlying Causes of Changes on Projects
Start improving your change management skills by creating some categories of the underlying causes of changes your company experiences.