Understanding the Construction Field Day

For a contractor to truly improve their field productivity, they must start with understanding how the time is spent.

D. Brown Management Profile Picture
Share

Depending on the trade, project, and the labor, study the time spent on actual installation ranges from 50-64%.  

Field Productivity: Understanding the Construction Day from the Field Perspective. Increase actual installation to 70% means almost 10% increase in production.

Remaining time is spent on non-installation activities including material logistics, movement around the jobsite, breaks, layout, mobilization to the work area, etc.  

These labor studies include craft labor and direct supervision at the foreman level.  

An average amount of rework and typical jobsite conditions are all factored into these studies.  

These form the basis for the labor units all contractors use to estimate projects.   

Assuming our quantity take-offs are accurate, this is why multiple contractors can be so incredibly close in a competitive bidding situation.

Projects are then budgeted with these labor units and we manage projects to meet these budgets.  

BOTTOM LINE

There is a significant amount of non-installation time built into the labor units the whole industry uses. Just increasing the actual installation time by a few minutes will make a contractor significantly more competitive and profitable.

Create the Perfect Field Day

 

 


Understanding the Construction Field Day
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Understanding the Construction Field Day
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Lean Principle - Understanding Lean Construciton
Lean is a body of knowledge dating back hundreds of years focused on sustainably growing an organization. During the last 20 years the construction industry has been rapidly adopting some of these tools to improve productivity.
5-Step Foreman Coaching Outline
Accelerating the development of foremen is one of the most critical things a contractor can do to improve project outcomes and mitigate the craft labor shortage. This 5-step outline will form the foundation of a great coaching program.
Percent Planned Complete (PPC) - Calculation Example
Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.” This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement.